Tuesday, 16 April 2013
SEAREPA 2012
The Babalitan Micro-Hydro System is Now Online!
October 2012
The Babalitan micro-hydro project went live in October, and here are some images from the day of the commissioning ceremony!
The Babalitan micro-hydro project went live in October, and here are some images from the day of the commissioning ceremony!
Tuesday, 18 September 2012
The Kg. Babalitan Micro-Hydro Project Nears Completion
The 5 kilowatt micro-hydro turbine in the Murut village of Kampung Babalitan, Sabah is now installed and up and running. A few finishing touches remain to be made, including the addition of several more pipes (the Babalitan MHP has two intakes), and the completion of the electrical distribution system. We expect the system to be fully operational within the month, with the formal launching to be held this October.
After completion, the system will be delivering 24-hour electricity to the homes of Kg. Babalitan's 200 residents. When power is not needed in the day-time, residents have the option of utilizing the turbine's mechanical energy to power a rice mill that has been integrated with the system.
This project will be the 5th of its kind in the Pensiangan district to have been implemented by local villagers. These projects have been facilitated by TONIBUNG with support from organizations PACOS Trust, JOAS,
Aru Bumi Sabah and Green Empowerment.
5 village-based operators are being trained to maintain and manage the system. They will be able to perform any basic maintenance and repairs, and will be in communication with TONIBUNG staff after the project has been completed.
![]() |
| The People of Kg. Babalitan put the finishing touches on the 5kilowatt turbine. |
Monday, 17 September 2012
Introducing the Long Lamai Micro-Hydro Project
Long Lamai is located in the Ulu Baram area of Sarawak, a rainforest that has been conceded to logging companies for the past twenty years, in spite of protests of the indigenous Kenyah, Kayan, Saban, Punan, Kelabit and Penan tribes that have resided in the area for generations.
The village of Long Lamai houses over 400 sedentary Penan people, who subsist off of rice and forest products such as the sago palm. Their ancestral rainforest lands have been systematically exploited by the timber company Samling since the late 1990's, but the remaining Penan have managed to adapt to the changing times under the visionary leadership of their young head man, Wilson Bian Belare and his father, Belare Jabu before him.
In partnership with UNIMAS (the University of Malaysia Sarawak), staff and volunteers from TONIBUNG, the Borneo Project and Green Empowerment will be in Long Lamai for the next 3 months to facilitate the construction of a 16 kW micro-hydro power system. The system will provide the residents of Long Lamai with 24-hour renewable electricity and continue to demonstrate to Malaysia's government and the public that development need not come at the expense of indigenous peoples and the natural environment. UNIMAS and TONIBUNG have already been working in Long Lamai for several months, constructing a solar-powered village telecenter that enables broadband and telephone access in this remote village. With renewable power at the telecenter, all that's left is to provide electricity to the 400 village residents.
As with all TONIBUNG projects, the community is at the helm. TONIBUNG and its partners only play a consultative role in the process, while the locals, who know their forests, rivers and people better than anyone else, are responsible for managing, maintaining, and in large part, building the system.
Stay tuned to this blog for more updates on the Long Lamai Micro-Hydro Project.
*All photographs courtesy of Sze Ning of Center of Orang Asli Concerns.
The village of Long Lamai houses over 400 sedentary Penan people, who subsist off of rice and forest products such as the sago palm. Their ancestral rainforest lands have been systematically exploited by the timber company Samling since the late 1990's, but the remaining Penan have managed to adapt to the changing times under the visionary leadership of their young head man, Wilson Bian Belare and his father, Belare Jabu before him.
In partnership with UNIMAS (the University of Malaysia Sarawak), staff and volunteers from TONIBUNG, the Borneo Project and Green Empowerment will be in Long Lamai for the next 3 months to facilitate the construction of a 16 kW micro-hydro power system. The system will provide the residents of Long Lamai with 24-hour renewable electricity and continue to demonstrate to Malaysia's government and the public that development need not come at the expense of indigenous peoples and the natural environment. UNIMAS and TONIBUNG have already been working in Long Lamai for several months, constructing a solar-powered village telecenter that enables broadband and telephone access in this remote village. With renewable power at the telecenter, all that's left is to provide electricity to the 400 village residents.
As with all TONIBUNG projects, the community is at the helm. TONIBUNG and its partners only play a consultative role in the process, while the locals, who know their forests, rivers and people better than anyone else, are responsible for managing, maintaining, and in large part, building the system.
Stay tuned to this blog for more updates on the Long Lamai Micro-Hydro Project.
![]() |
| Consultation with village and project leaders. |
![]() |
| Scouting the lay of the land in preparation for construction of the civil and electrical distribution system. |
![]() |
| Long Lamai's residents give their undivided attention at a village meeting. |
![]() |
| Garen of Long Lamai discusses the micro-hydro project at the community telecenter. |
![]() |
| Johan Sipail of TONIBUNG learns how to play the keringot, the Penan nose flute. |
Monday, 25 June 2012
Distinguished Energy Professor Daniel Kammen joins Sabah's Indigenous Peoples in the Fight for Clean Energy
![]() |
| Crossing the Papar River |
In the spirit of supporting Sabah’s transition into community-based renewables, Daniel joined TONIBUNG, Green Empowerment and LEAP representatives in a trek through the Crocker Range rainforest. The destinations were the micro-hydro powered villages of Terian and Buayan. The micro-hydro power systems (5 KW and 10KW respectively), are owned, managed and maintained by the people of Terian and Buayan, and supported by community organizations PACOS Trust and TONIBUNG (Friends of Village Development).
| Daniel, Adrian Lasimbang of TONIBUNG and Gabriel Wynn of Green Empowerment at Irene Tani's house with the people of Kampung Buayan after community consultations |
| Daniel, Johan of Kampung Terian and Ginus, micro-hydro operator of Kampung Buayan with Buayan's Micro Hydro Turbine |
Daniel and the team were quick to highlight the importance of Buayan continuing to take the lead in developing their community using renewable resources, and more importantly, to share their ideas and experiences with other communities. They also stressed that the story of Buayan- both in terms of their struggle in opposing the Kaiduan dam, and in terms of their ability to take their village’s sustainable development into their own hands- needed to be told. The SEAREPA will be one space where the voices of Buayan, and others like them throughout Southeast Asia, will be heard.
| Making the last crossing home on the Papar River |
Friday, 18 May 2012
Micro Hydro Pre-Feasibility study at Tabin
On 8-9th May, we conducted a micro hydro site pre feasibility study at Tabin wildlife sanctuary for Borneo Rhino Alliance (BORA). we visited four possible sites around the Tabin wildlife complex. The goal is to find a suitable site to build a micro hydro system that could replace the ageing diesel generators at Tabin. Apart from knowing the hydro potential in Tabin, it was a very educational visit for my team especially on wildlife and conservation of the critically endangred Sumatran Rhinos... lots of sharing from our very dedicated host..senior wildlife conservationist Dr Payne and Dr Zainal.
site location
beautiful water fall at site 3
a majestic water fall at site 2... unfortunately too good to be spoiled for micro hydro
Panaromic view of the site 4.. this is the site that have potential up to 40Kw
meeting si Puntung.. the female Sumatran Rhino currently at Interim Rhino Facility. Si Puntung lost one of her front feet from a poacher's snare.
not very hard to spot wildlife at this place.. they even come to you!
i hope to come back again to Tabin.. look forward for a micro hydro project at this great conservation place..
Monday, 30 April 2012
MHP Turbines Pre-delivery test
We are proud to announce that the Pre-delivery test of the turbine for Babalitan MHP have been a success. hopefully by July we can get the turbine on site and ready for installation and commisioning.
The nearly completed turbine for Long Lamai
Representatives from Ranhill to observe the pre-delivery test of Babalitan MHP turbine
Turbine for Babalitan MHP undergoing test at HEKSA Hydro Facility in Bandung, Indonesia